Minggu, 17 April 2016

1.2. Mobilisasi

ITEM PEMBAYARAN NO. :  1.2
JENIS PEKERJAAN :  MOBILISASI
           HARGA   JUMLAH 
No. U R A I A N   SAT VOL.  SATUAN   HARGA 
         (Rp.)   (Rp.) 
A. Sewa Tanah   M2 1                    500                    500
B. PERALATAN          
  Periksa lembar 1.2-2            260.300.000
C. MOBILISASI FASILITAS KONTRAKTOR     1              50.000              50.000
1 Base Camp  
2 Kantor  
3 Barak  
4 Bengkel  
5 Gudang, dan lain-lain  
6 . . . . . . . . . . . . . . . . . . . . . . . . . .  
D. MOBILISASI FASILITAS LABORATORIUM   set 1      55.940.000      55.940.000
1 Ruang Laboratorium (sesuai Gambar)  
2 Soil & Aggregate Testing  
  Compaction Test  
  CBR Test  
  Specific Gravity  
  Atterberg Limits  
  Grain Size Analysis  
  Field Density Test by Sand Cone Methode  
  Moisture Content  
  Abrasion of Aggregate by Los Angeles Machine  
3 Bituminous Testing  
  Marshall Asphalt Test  
  Extraction Test, Centrifuge/Refflux Method  
  Specific Gravity for Coarse Aggregate  
  Specific Gravity for Fine Aggregate  
  Mix Air Viod Content (Accurate Method)  
  Core Drill  
  Metal Thermometer  
  Accessories and Tolls  
  Penetration Test  
  Softening Point  
  Refusal Density Compactor  
4 Concrete Testing  
  Slump Cone   
  Cylinder/Cube Mould for Compressive Strength  
  Beam Mould for Flexural Strength (RIGID)  
  Crushing Machine  
5 Pendukung (Periksa Fasilitas Laboratorium)  
6 Operasional (Periksa Fasilitas Laboratorium)  
E. MOBILISASI LAINNYA          
E.I. PEKERJAAN DARURAT LS 1    100.000.000    100.000.000
1 Perkuatan Jembatan Lama  
2 Pemeliharaan Jalan Kerja / Samping  
3 . . . . . . . . . . . . . . . . . . . . . . . . . .  
4 . . . . . . . . . . . . . . . . . . . . . . . . . .  
5 . . . . . . . . . . . . . . . . . . . . . . . . . .  
6 . . . . . . . . . . . . . . . . . . . . . . . . . .  
   
E.II. LAIN-LAIN Set 1        5.000.000        5.000.000
1 Komunikasi Lapangan Lengkap . . . .  
2 . . . . . . . . . . . . . . . . . . . . . . . . . .  
3 . . . . . . . . . . . . . . . . . . . . . . . . . .  
4 . . . . . . . . . . . . . . . . . . . . . . . . . .  
5 . . . . . . . . . . . . . . . . . . . . . . . . . .  
6 . . . . . . . . . . . . . . . . . . . . . . . . . .  
F. Manajemen dan Keselamatan lalu lintas       LS        5.000.000
G. DEMOBILISASI   LS 1      78.090.000      78.090.000
  Total Biaya Mobilisasi            504.380.500
Catatan :
Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. :  1.2
JENIS PEKERJAAN                                   :  MOBILISASI   B. PERALATAN
 Lembar 1.2-2 
    KODE      HARGA   JUMLAH 
No. JENIS ALAT ALAT SAT VOL.  SATUAN   HARGA 
           (Rp.)   (Rp.) 
B. PERALATAN          
1 ASPHALT MIXING PLANT E01 Unit 1    200.000.000    200.000.000
2 ASPHALT FINISHER E02 Unit 1            500.000            500.000
3 ASPHALT SPRAYER E03 Unit 1            100.000            100.000
4 BULLDOZER 100-150 HP E04 Unit 1            500.000            500.000
5 COMPRESSOR 4000-6500 L\M E05 Unit 1            150.000            150.000
6 CONCRETE MIXER 0.3-0.6 M3 E06 Unit 1            100.000            100.000
7 CRANE 10-15 TON E07 Unit 1            150.000            150.000
8 DUMP TRUCK 3.5 TON E08 Unit 18            150.000        2.700.000
9 DUMP TRUCK 10 TON E09 Unit 5            150.000            750.000
10 EXCAVATOR 80-140 HP E10 Unit 3            500.000        1.500.000
11 FLAT BED TRUCK 3-4 M3 E11 Unit 1            150.000            150.000
12 GENERATOR SET E12 Unit 1            300.000            300.000
13 MOTOR GRADER >100 HP E13 Unit 1            500.000            500.000
14 TRACK LOADER 75-100 HP E14 Unit 1            500.000            500.000
15 WHEEL LOADER 1.0-1.6 M3 E15 Unit 1            500.000            500.000
16 THREE WHEEL ROLLER 6-8 T E16 Unit 2            500.000        1.000.000
17 TANDEM ROLLER 6-8 T. E17 Unit 1            500.000            500.000
18 TIRE ROLLER 8-10 T. E18 Unit 1            500.000            500.000
19 VIBRATORY ROLLER 5-8 T. E19 Unit 1            500.000            500.000
20 CONCRETE VIBRATOR E20 Unit 5              50.000            250.000
21 STONE CRUSHER E21 Unit 1      40.000.000      40.000.000
22 WATER PUMP 70-100 mm E22 Unit 2              50.000            100.000
23 WATER TANKER 3000-4500 L. E23 Unit 1            150.000            150.000
24 PEDESTRIAN ROLLER E24 Unit 1              50.000              50.000
25 TAMPER E25 Unit 1              50.000              50.000
26 JACK HAMMER E26 Unit 2              50.000            100.000
27 FULVI MIXER E27 Unit 1            500.000            500.000
28 CONCRETE PUMP E28 Unit 2            500.000        1.000.000
29 TRAILER 20 TON E29 Unit 2        1.000.000        2.000.000
30 PILE DRIVER + HAMMER E30 Unit 2        1.000.000        2.000.000
31 CRANE ON TRACK 35 TON E31 Unit 2        1.000.000        2.000.000
32 WELDING SET E32 Unit 2            200.000            400.000
33 BORE PILE MACHINE E33 Unit 1            500.000            500.000
34 ASPHALT LIQUID MIXER E34 Unit 1            300.000            300.000
35 TRONTON E35 Unit      
36 COLD MILLING MACHINE E37 Unit      
37 ROCK DRILL BREAKER E36 Unit      
38 COLD RECYCLER E38 Unit      
39 HOT RECYCLER E39 Unit      
40 AGGREGAT (CHIP) SPREADER E40 Unit      
41 ASPHALT DISTRIBUTOR E41 Unit      
42 SLIP FORM PAVER E42 Unit      
43 CONCRETE PAN MIXER E43 Unit      
44 CONCRETE BREAKER E44 Unit      
45 ASPAHLT TANKER E45 Unit      
46 CEMENT TANKER E46 Unit      
47 CONDRETE MIXER (350) E47 Unit      
48 VIBRATING RAMMER E48 Unit      
49 TRUK MIXER (AGITATOR) E49 Unit      
50 BORE PILE MACHINE E50 Unit      
51 CRANE ON TRACK 75-100 TON E51 Unit      
  Total untuk Item B pada Lembar 1            260.300.000
MOBILISASI FASILITAS LABORATORIUM
SATUAN PENGUKURAN : Lump sum
HARGA SATUAN : Rp.       55.940.000
NO. URAIAN SATUAN VOLUME SAT TOTAL KETERANGAN
             
I. Laboratory Building          
1. Laboratory Building m2 108 55000        5.940.000  
II. Soil & Aggregate Testing     Rp      10.000.000  
1. Compaction Test  
2. CBR Test  
3 Specifc Gravity  
4 Atterberg Limits  
5 Grain Size Analysis  
6 Field Density Test by Sand Cone Methode  
7 Moisture Content  
8 Abrasion of Aggregate by Los Angeles Machine  
III. Bituminous Testing     Rp      10.000.000  
1. Marshall Asphalt Test  
2. Extraction Test, Centrifuge/Reflux Method  
3 Specific Gravity of Coarse Aggregate  
4 Specific Gravity of Fine Aggregate  
5 Mix Air Viod Content (Accurate Method)  
6 Core Drill  
7 Metal Thermometer  
8 Accessories and Tolls  
9 Penetration Test  
10 Softening Point  
11 Refusal Density Compactor  
IV. Concrete Testing     Rp      10.000.000  
1 Slump Cone   
2 Cylinder/Cube Mould for Compressive Strength  
3 Beam Mould for Flexural Strength  
4 Crushing Machine  
V. Peralatan pendukung     Rp      10.000.000  
1 Mobil Pick Up  
2 Komputer + Printer  
3 Furniture  
VI. Operasional          
VII. Test Luar     Rp      10.000.000  
  Test Luar, sesuai kebutuhan atau atas  
  perintah Direksi   
  TOTAL BIAYA MOBILISASI     Rp      55.940.000  
Catatan :
1. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar kontrak) dan biaya lain-lainnya.
2. Test luar adalah test ke lembaga pengujian yang disetujui oleh Konsultan Pengawas.

Tidak ada komentar:

Posting Komentar